File
Operations: Export Tasks to Text File or Word Document (for ProjectMaster
3.5)
To Text
File -
After
you've entered your project plan in ProjectMaster, you may want to work
with the tasks in other programs such as Microsoft© Excel or Project.
We've added the Export Tasks feature for this purpose. Simply select the
File menu and the Export Tasks option and you'll be given a file/save
dialog. Select your target location and OK to finish.
Tasks are
exported in standard, tab-delimited text. To import to Microsoft Project:
Open
MSProject to a new project file.
Select Open
from the File menu.
In the Open
dialog, change the File Type to Text (tab delimited) and select the text
file you exported from ProjectMaster.
- Select
New Map.
- Change
the Import/Export Map Name: to Cadence.
- Make
sure Tasks is selected in the Data to Import box.
- Make
sure Export Header Row/Import Includes Headers is selected.
- Select
Task Mapping tab.
- Map
tasks to MSProject by selecting the appropriate field dropdown. Follow
the table below:
|
To: Microsoft Project |
From: Text File Field |
Data Type |
| WBS |
WBS
Number |
Text |
| Name |
Activity Name |
Text |
| (Do
Not Map) |
Planned Start Date |
Text |
| (Do
Not Map) |
Planned Finish Date |
Text |
| (Do
Not Map) |
Potential Early Start Date |
Text |
| (Do
Not Map) |
Planned Slip Date |
Text |
| (Do
Not Map) |
Actual
Finish Date |
Text |
With the
new Cadence map selected, select open.
For details
on how to manipulate text files in other applications, please consult
their application help system or manual.
Export
Operations:
Exporting to
Microsoft®
Project
ProjectMaster 3.5 supports exporting your schedule to Microsoft Project
2000. Simply select Export to MS Project from the File menu and choose
your sort preference from the dialog above.
You have two options when it comes to exporting your tasks from
ProjectMaster: Sorting tasks in WBS order from your Work Breakdown
Structure or, if you've already sequenced your tasks in the Schedule
Sequence Editor, you can export your tasks in schedule order. This second
option is only available if you've actually scheduled some of your tasks.
If you haven't gotten that far, the Schedule Order option will be grayed
out. If you've sequenced some of your tasks but haven't finished, you will
be able to export in schedule sequence order, with your unsequenced tasks
sorted at the bottom of your Microsoft Project task list in WBS order.
If you select to export your schedule in WBS order, major blocks in
ProjectMaster will be converted to summary tasks, with each block's tasks
appearing after its block. If you select to export your schedule in
Schedule order, the major blocks will be converted to milestones, with
each milestone appearing after the last scheduled task in its block.
Remember where
you save your file as it won't open in Microsoft Project automatically.
Open the exported Microsoft Project 2000 file and you will see all your
ProjectMaster task levels, block through work package.
Microsoft Project Default Column Set:
Information (blue-circled "i")
Contains information associated with a given task item. For example, any
tasks that were marked "Complete" in ProjectMaster will be marked with a
Check here.
Assumptions entered at the task level in the Schedule and Constraints
Editor in ProjectMaster are imported into Microsoft Project as notes.
You'll identify a task with an assumption by the yellow note icon in its
Information column. Any project level Issues and Assumptions are attached
as notes to the Project Timeline, the first line of your Microsoft Project
schedule.
Task Name, Duration, Start, Finish
These are
imported directly from ProjectMaster untouched.
Predecessors
Microsoft Project will take your ProjectMaster predecessors from the
Schedule and Constraints editor and place the data in this column. The
schedule view will display the predecessor relationships with their
correct lines and arrows. Critical Impact data is not imported from
ProjectMaster and will not be drawn in Project.
Resources
Resources are imported from ProjectMaster with the associated workload
assignments in tow: responsible resources for a given task are listed
first in the Resources column, with contributors to follow.
WBS Numbers
Microsoft Project handles WBS numbers differently than ProjectMaster.
Because of this, ProjectMaster exports WBS numbers to a standard text
field into Microsoft Project called TEXT1, which you'll have to add
manually to your schedule. Here's how:
1. In your Microsoft Project file, click the "Task Name" column heading to
select the column.
2. Right-click the highlighted "Task Name" column.
3. Select "Insert Column" from the pop-up menu.
4. In the "Insert Column" dialog, select "TEXT1" in the "Field Name"
drop-down. In the "Title" field, type "WBS #"
5. Click OK.
You should now see your WBS numbers in the column to the left of the Task
Name column.
Exporting
Plan to Word 2000

You can
also export your entire project plan to Microsoft Word 2000 for electronic
distribution to team members and managers who aren't running ProjectMaster
locally. Just select Export to Word from the File menu and finalize
settings in the simple dialog above.
You'll
notice that you only have options for the graphical components of your
plan: Work Breakdown Structure, Responsibility Matrix, and Schedule.
While the
text in the exported Word project plan is editable, the graphical
components are not. ProjectMaster exports these as image files to save in
file size and complexity.
