|

Schedule
Sequence Editor

Once you
have your tasks with roles and responsibilities assigned, it's time to
sequence your schedule.
WBS
Sequence
On the left, you'll see your tasks in order as they were entered in
the Work Breakdown Structure editor, with block titles separating each
block's activities. To begin sequencing, select a task in the left pane
and click the right Move button to transfer it to the right pane, your
sequenced schedule. You can also search for tasks by WBS number in the
search box above the WBS Sequence pane.
Schedule
Sequence
On the right, you'll see your sequenced tasks and the addition of a
new column for sequence number. By default, when you select an item from
the left and move it to the sequenced task list, the new task falls as the
next item immediately following the currently selected item on the right.
You can also search for tasks by sequence number in the search box above
the Schedule Sequence pane.
Blocks =
Milestones
As soon as you sequence the last task in a given block, the block is
automatically moved next and promoted to milestone. The milestone will
appear on your schedule as a diamond and the finish date will be
determined by the finish date of the last task to be completed in that
block.
Schedule & Constraints Editor

Your tasks are
now sequenced in roughly the order the work will be done. It’s time to
attach more detailed scheduling data to your schedule.
From left to right across the editor you'll select the task to schedule,
enter date information, choose dependencies and critical impacts, and add
assumptions.
Schedule
In the
schedule pane, you'll see your sequenced tasks with blocks grayed out.
Here, select the task you'd like to schedule and begin selecting
appropriate dates for Planned Start, Planned Finish, Potential Early
Start, Slip, and Actual Finish. If you can't see enough of the task in the
small pane, just hover your cursor over the task and wait a second for the
full text to pop up. You don't need to complete all of these fields
on your first pass through the schedule.
Though the block level items, Milestones, are displayed on the schedule
here, you won't be able to do anything with them. Milestones capture their
schedule data from that of the tasks beneath them. A milestone is
scheduled as a diamond on the same finish date as that block's last
finished task.
Constraints
After you've
entered the preliminary schedule data for the selected task, you can then
assign dependencies on the Constraints side of the editor.
As you schedule, you'll notice that the Activity to View pane under
Constraints on the right has been populating with tasks that have already
been sequenced above your currently selected task.
For example, in the image above notice task sequence number 5 selected in
the left pane, "Create Budget for..." has a planned start of August 1, and
a planned finish of August 3. In the Activity to View pane on the right,
the tasks sequenced before task 5 are now visible.
These are tasks that may need to be completed prior to starting task 5,
also known as task 5's Predecessors. In the example above, task sequence
number 1, "Create Budget for Phones" has been selected and added to the
Dependencies pane on the far right indicating that task 5 cannot begin
until task 1 is complete.
On your printed Schedule, you'll see a single arrow drawn down from the
end of task 1 to the beginning of task 5 indicating this dependent
relationship.
Note: Tasks can have more than one dependency, and will have multiple
arrows highlighting those relationships drawn on the Schedule.
Critical Impact
A Critical
Impact task is a task that, if slipped, may jeopardize the overall project
timeline. If you check this box while scheduling a task, an up arrow will
be drawn from the end of the task all the way to the project timeline. If
you check the Critical Impact box while scheduling a subtask, an up arrow
will be drawn from the end of the subtask to the task timeline. The same
logic holds true for work packages.
Assumptions
Any assumption in the text box will be displayed in the Assumptions column
on your schedule. Use assumptions to track key information that may affect
work on the task.
Schedule Layout Editor

The
Schedule Layout Editor lets you control the display of your schedule on
screen and on paper.
Select
Level of Activity to Display (and Print)
- All
Activities
This option displays all project activities.
-
Activities to Sub-Tasks
This option allows you to collapse the work package detail for a cleaner
schedule view.
-
Activities to Tasks
This option allows you to collapse all sub-task activity.
-
Milestones Only This option allows you to collapse all project activity
to the milestone level, a useful view for management or steering
committee presentation.
Columns
to Display
-
Assumptions
Displays all assumptions identified on the schedule
-
Responsible Initials
Displays the initials of the (responsible) Circle-dot person for each
task
-
Potential Early Start Date
Displays Potential Early Start column on the schedule
- Planned
Start Date
Displays Planned Start column on the schedule
- Planned
Finish Date
Displays Planned Finish column on the schedule
- Slip
Date
Displays Planned Slip column on the schedule
- Actual
Finish Date
Displays Actual Finish column on the schedule
-
Dependency
Displays Dependency column on the schedule
- Sequence
Number
Displays schedule sequence number column on the schedule
- Calendar
Displays Calendar portion of the schedule
Date
Display Options
Allows you
to change the scale of the date display on the header of the calendar
portion of the schedule. The Begin Week On option will activate if you
choose to view your schedule by Year/Month/Week. This will let you set
your schedule to run Monday through Sunday or Friday through Thursday. If
most of your tasks start and end on Monday or Friday, a schedule starting
on either of those days will make for a more organized view.
Shade
Weekends and Holidays
Choose to
shade all weekends on your schedule, or add your own custom date ranges.
Make sure to capture key trade events or organizational obligations that
may affect the work on your project.

|